It appears to have taken 16 years to complete the
main sewers of Clark’s Scheme. By 1875 nearly
38 miles of brick and 37 miles of stoneware pipe sewers were constructed. The
pumping plant at Palmer’s Bridge comprised two 30 and one 45 PHP vertical
centrifugal steam pumps and two huge silt-pits provided with penstocks. These
penstocks also shut off the flow of the sewers from the channel to the
Beliaghata Canal. During the rainy season they were opened so that the sewers
could discharge fully into the canal providing a great relief from storm-water
overflows between Upper Circular Road sewer and the Circular Canal. The drainage
works of the Southern Division were finally completed in 1878 and those of the
Northern Division between 1885-86.
Clark’s original scheme was not complete when the
Corporation was compelled to undertake additional works to prevent the
discharge of storm-water into the canal. Calcutta’s Canals (Circular, New Cut,
Bhangur Khal, Kestopur and Tolly’s Nullah) though excavated principally for
navigation, helped in draining the City to a considerable extent by carrying
storm-water until the end of the nineteenth century. In 1880, however, the
Government Irrigation authorities objected to the storm-water being discharged
into the canal, although there could be no doubt that the canal had intercepted
the natural surface drainage channels of the city. The Government in 1881-82 stopped the
discharge of storm water into the Circular Canal. The city drainage was thus
disoriented and the escapes into the Circular Canal had to be checked by a long
intercepting sewer that diverted the drainage to the existing Town Head Cut.
After a long controversy with the Government the
Corporation reluctantly agreed in 1881 to: (i) construct an intercepting sewer
to increase the dimension on the outfall channel (the open cut) to a capacity
of about 90,000 cubic feet per minute; (ii) to construct tide-gates of four
openings 10 feet wide at Makalpotta; and, (iii) to divert the storm-water of
the northern area of the city to the Beliaghata Canal below Dhapa.
This intercepting sewer ran parallel with and close
to the canal from Habsi Bagan Road to Palmer’s bridge, where it joined the
outfall channel. But unfortunately it was constructed, like most of the city
sewers, with the smaller sections joining the larger invert to invert and the
levels at which it was constructed did not allow it to take the required
discharges from the storm overflows without causing the water to stagnate in
the low-lying areas of the city. There
were 37 miles of main or brick sewers and 147 miles of pipe sewers in Calcutta
by 1890.
The Added and Fringe Areas, covering 8188 acres,
were incorporated in the town of Calcutta in 1889. The development of these
areas was entrusted to a committee, called the Suburban Improvement Committee. For
the purpose of drainage the new areas fell naturally into 3 blocks:
I.
The
portion west and south of Tolly’s Nullah, including the new docks. This drained
towards the south and southwest;
II.
The
area east of Tolly’s Nullah, including Ballygunge and Entally. This drained
towards the Bidyadhari; and
III.
The
area lying between the Circular canal, Circular Road and the Eastern Bengal
State Railway lines, devoid of all drainage except in so far as the drains of
Calcutta provided outlets
Under the Suburban Sewerage Scheme executed between
1891 and 1906, 12.5 square miles (32 sqkms) in the newer southern areas of the
city were covered. A new pumping station was constructed at Ballygunge and the
capacity of the Palmer’s Bridge station augmented. The drainage system could,
therefore, dispose off storm-water from one-fourth of an inch rainfall per hour
plus 40 gallons of sewage per inhabitant per day. This ‘combined drainage’ flow was brought
through the underground sewerage network to Palmer’s Bridge and Ballygunge
pumping stations. It was then pumped into high-level sewers meeting at a place called
“Topsia A”. From here, the discharge flowed by gravity directly into Raja Khal,
a creek of the tidal river Bidyadhari.
Burdened with the outfall of the entire city’s
drainage system, the Bidyadhari began to show signs of rapid deterioration. In
1928, the Government declared it to be a dead river. The city was thence almost
trapped in a drainage deadlock. At this juncture, Dr Birendranth Dey (1891-1963) came up with a new scheme for both the outfall
and the internal drainage system. The Outfall Scheme comprised of:
I.
Lined
dry-weather flow channel from Topsia A to the river Kultigong at Ghusighata,
discharging into the river through a sluice at the outfall
II.
Storm-water
flow channel (the Suburban Head Cut) from Ballygunge drainage pumping station
to the Kultigong at Ghusighata, discharging through the above mentioned sluice
III.
Storm-water
flow channel (the Town Head Cut) direct from Palmer’s Bridge Pumping Station,
joining the dry-weather flow channel near Topsia A at Bantala, where provision
was made for two sedimentation tanks for primary treatment of the dry-weather
flow
IV.
Storm-water
flow channel from the Dhapa lock pumping station, joining the channel with the
above mentioned one at Makalpota
This Scheme was commissioned
only in 1943. It has since undergone major modifications and expansion to meet
the rapid growth of the city’s area and population.
concluded
No comments:
Post a Comment